1
Eligibility Verification
City of Tallahassee (COT) Water Resources Engineering staff reviews eligibility application to verify eligibility. See if you are eligible.
2
Applicant Submits Grant Application
Property owner submits complete application and required documentation to COT Customer Operations.
3
Applicant Review and Approval
COT Customer Operations reviews application and sends approval letter to owner and plumber.
4
Plumber Obtains Plumbing Permits
COT Growth Management issues plumbing permit. Plumber obtains all of the applicable permits.
5
Plumber Completes Sewer Connection
Plumber performs sewer connection and septic tank abandonment. Growth Management conducts final inspection.
6
Customer Operations Pays Plumber
COT Customer Operations releases payment to plumber.
7
COT Starts Billing Sewer Charge
COT starts monthly sewer charge through utility bill.